Standard Procedure /Steps for Registration of Steam/feed/blow down line | ||||
Sl.No. | Procedure/Step | Forms Required/Documents Required | Timelines | Fees |
1 | Apply for Registration of pipeline | 1) Layout drawing of Steam/Feed/blowdown line in triplicates, showing position of pipe fittings. 2) Details of materials dimension and specifications of pipes and pipe fittings. 3) Welding details of joints. | ||
2 | Concerned Officer will verify and examine the drawings and documents and forward the same alongwith a draft approval letter to Chief Inspector for approval. | Within 7 days of receiving the drawings and documents | ||
3 | Approval of drawings by Chief Inspector | 1 set of approved drawing issued to the owner. | Within 15 days | Payment of the fee for pre-scrutiny of drawings. |
4. | Submission of application for approval of proposed contractor. | 1) Submission of Proforma-II regarding approval of contractor . 2) Details of manpower, tool and tackles and credentials of contractor , to be employed in the job. 3) Copy of certificates of welder (in Form-XIII) of all welders. | ||
5. | Verification of documents by concern officer and forwarding to Chief Inspector for approval. | Within 7 days | ||
6. | Approval of contractor for erection and fabrication of pipeline by Chief Inspector. | 2 working days | ||
7. | Submission of documents regarding materials | Test Certificate of pipes and its fittings in IBR form. | ||
8. | Conducting materials inspection and performance /stimulation test of welder (if required). | Within 7 days. | ||
9. | Concern officer will carry out all stage inspections during fabrication and erection as per Regulation | 1) Conducting NDT, if required 2) Conducting PMI testing of materials , if required. | As per convenience of owner | |
10. | Final inspection of pipeline network as per Regulation. If there is any deviation to approved drawings the owner would be asked to submit AS BUILT drawings for approval. | Erection completion report is to be submitted by owner/ Erector along with- i) Radiographic films, if applicable. ii) Post weld heat treatment report if applicable . | Within 7 days | Fee for inspection of Steam Pipeline. |
11. | Conducting hydraulic test of pipelines and Granting of charging order. | Application for offering hydraulic test. | Within 7 days | |
12. | Granting Registration to Steam Pipeline by Chief Inspector. | Within 7 days |